project introduction

In January of 2024, a private Australian developer, HMC StratCorp (the Applicant), with their subsidiary DigiCo REIT, proposed building a hyperscale data center. This is a facility housing computer servers to be used to train AI, among other uses, at 1977 Saturn Avenue in Monterey Park. The project would operate 24 hours a day, 7 days a week, 365 days a year.

On October 31, 2024, HMC submitted an Initial Study (IS) and Mitigated Negative Declaration (MND) for this data center. In response to some feedback received on December 2, 2024 from organizations like Advocates for the Environment and others, HMC submitted revised technical details with design enhancements on October 27, 2025. The IS/MND is a streamlined environmental review process that allows projects to move forward quickly, but only if all impacts are deemed "less than significant."  For a facility of this scale, that conclusion deserves scrutiny.

The applicant's consultants prepared the IS/MND. They chose the assumptions, set the study boundaries, and selected the comparisons. Not surprisingly, they concluded their client's project poses no significant impacts. But "less than significant" is a legal threshold, not a measure of whether there are actual impacts or whether real people will be affected. 

Thresholds are imperfect measures of experienced reality.  

  • They are often arbitrary: Noise limits (54–56 dB) are set for regulatory convenience, not based on health research about sleep disruption or stress.

  • They may be outdated: Air quality thresholds don't always reflect current science on cumulative health effects.

  • Impacts below thresholds still cause harm: A continuous 50 dB hum 24/7 may comply with the law but still degrade quality of life.

  • "Mitigated" ≠ "Eliminated": Sound barriers reduce noise; they don't make it disappear. Biofiltration treats stormwater; it doesn't purify it.

project overview

what is being proposed

Location

1977 Saturn Avenue, Monterey Park, CA

Property/Lot Size

218,400 square feet (~4 football fields)

Peak Power Capacity

49.5–50 megawatts (MW)

Main Power Supplier

Grid service through SoCal Edison (SCE)

Backup Power

24 Tier 4 diesel generators

Cooling

23 rooftop chillers with a closed-loop water system

Timeline

Application submitted January 2024; hearings postponed indefinitely due to public pressure

estimated demand

Annual electricity use

~434 GWh/year

Equivalent to ~40,000 households

Annual water use

12 million gallons/year

Equivalent to ~120 households

Annual greenhouse gas emissions

77,034 metric tons CO₂e

2027 estimate; assumes SCE ⅔ grid carbon mixThe following figures come from the Initial Study (IS/MND) prepared by Kimley-Horn on behalf of the applicant. They are modeled estimates, not independently verified measurements.

Annual city tax revenue

~$5 million

~3% of total City revenue

Obtained from Century Urban Strategic Real Estate Advisory Services: 1977 Saturn Data Center Fiscal Revenue Analysis, August 12, 2025 [pages 333-347]

project timeline

June 2020

  • Monterey Park voters approve Measure JJ, designating Saturn Park for “Innovation / Technology.”

  • Existing zoning allows data processing, not explicitly data centers; heavy industrial uses remain prohibited.

April 2023

  • HMC contacts the City asking whether “data centers” qualify as allowed “data processing facilities.”

  • Assistant City Planner responds that they are equivalent.

September 2023

  • HMC seeks confirmation that no Development Agreement is required.

  • City Attorney provides no guarantees, but states one is not required, allowing HMC to proceed.

January 2024

  • HMC submits permit and design review applications for the data center.

April 2024

  • Planning Director flags that the proposed data center conflicts with Measure JJ, triggering internal reassessment of zoning.

May 2024

  • City forms SPARC to solicit community input on Saturn Park zoning.

  • Process signals an intent to amend zoning to accommodate data centers.

June 2024

  • City adopts a temporary moratorium on data centers.

  • HMC is granted an exception, allowing its project to continue.

July 29 – August 29, 2024

  • SPARC sessions are held.

  • Sessions include discussion of the Saturn Park data center despite City claims otherwise.

  • Outcome is a recommendation to pursue zoning amendments.

October 2024

  • City publishes a Mitigated Negative Declaration (MND) claiming no significant environmental impacts.

November 2024

  • City staff shift approach and require a Development Agreement, distinguishing data centers from data processing facilities.

  • City Attorney states no further environmental review is required if compliant.

December 2024 – September 2025

  • Nine-month gap with no publicly available documents released.

September 3, 2025

  • Public hearing adopts a Conditional Use Ordinance approving data centers at Saturn Park, contingent on a Development Agreement.

November 14, 2025

  • HMC requests a delay of the MND vote to December 3.

December 2, 2025

  • HMC sends an email pressuring City Council to approve the project, characterizing online criticism as “misinformation.”

December 3, 2025

  • HMC reverses course and requests a delay to January 21.

  • Monterey Park City Council grants the delay.

  • Monterey Park follows up by postponing the vote indefinitely to give HMC more time.